Amendment as follows (which is technically equivalent to the original DCR content).


APPENDIX A - AGREED DEVIATIONS FOR VISHAY S.A. DIVISION SFERNICE (F)
--------------------------------
Items Affected
................................................
Deviations from Final Production Tests (Chart II) (& Table 6)

................................................
--------------------------------
Description of Deviations
................................................
Para 9.1 Overload
An Initial Measurement shall be added as follows:
The resistance, RA, shall be measured, prior to application of the overload voltage, as specified in paragraph 9.5.1 of the Generic Specification.

During the Final Measurement the change in resistance compared to the Initial Measurement value, (delta)RA/RA, shall not exceed the following limit:
(delta)RA/RA limit : +/-(0.05 +0.05Ohm x 100/Rn)%

................................................
Para. 9.2 Third Harmonic Control And Current Noise
This test is not applicable







Changes

Menu

Are you sure you want to delete this menu item?

Optimized for:

© 2010 European Space Agency. All rights reserved.

About | Mission | Sitemap | Known Issues | Feedback | Disclaimer and copyright